Lift Station no. 10 Upgrades - Planning
Paradise, Newfoundland and Labrador
Federal contribution
$197,603
Federal share40%
of $494.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedNov 24, 2020
202120222023202420252026
Built
Approved 6 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of Paradise
- Construction start
- Oct 13, 2020(actual)
- Construction end
- Feb 14, 2026(actual)
Against the original forecast
- Construction start21 months earlyforecast Jun 30, 2022
- Construction end3 months earlyforecast May 15, 2026