Main Street Road Upgrade
Bishop's Falls, Newfoundland and Labrador
Federal contribution
$97,808
Federal share26%
of $379.2K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 18, 2021
2021
Built
Approved 13 months before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Town of Bishops Falls
- Construction start
- Aug 3, 2021(actual)
- Construction end
- Oct 15, 2021(actual)
Against the original forecast
- Construction start2 months lateforecast May 24, 2021
- Construction end4 months lateforecast Jun 11, 2021
Also in Bishop's Falls
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56764 in the federal list. How to read these figures.