Tipping Drive Waterline
Pasadena, Newfoundland and Labrador
Federal contribution
$202,959
Federal share40%
of $507.4K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 16, 2020
2021
Built
Approved 3 weeks before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of Pasadena
- Construction start
- Jun 7, 2021(actual)
- Construction end
- Sep 2, 2021(actual)