Recreation Facilities Upgrades

Pasadena, Newfoundland and Labrador

completeRecreationCCRIS
Federal contribution
$160,240
Federal share33%

of $480.6K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 16, 2020
2021202220232024
Built

Approved 3 weeks before the announcement.

Program
Community, Culture & Recreation Infrastructure Stream
Ultimate recipient
Town of Pasadena
Construction start
Jun 26, 2023(actual)
Construction end
Aug 1, 2024(actual)

Against the original forecast

  • Construction start11 months earlyforecast Jun 3, 2024
  • Construction end7 weeks earlyforecast Sep 18, 2024