Greenridge Road Waterline Loop

Bishop's Falls, Newfoundland and Labrador

completeDrinking WaterGIS
Federal contribution
$40,703
Federal share40%

of $101.8K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 25, 2021
20202021
Built

Approved 12 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of Bishop’s Falls
Construction start
Jan 16, 2020(actual)
Construction end
Nov 30, 2020(actual)

Against the original forecast

  • Construction start12 months earlyforecast Jan 16, 2021
  • Construction end8 weeks earlyforecast Jan 27, 2021