Construction of a New Sports Complex - Sorel-Tracy
Federal contribution
$10.4M
$10,365,333
Federal share34%
of $30.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 22, 2021
today
202220232024202520262027
BuiltForecast
Approved 2 months before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- City of Sorel-Tracy
- Construction start
- Sep 5, 2024(forecast)
- Construction end
- Apr 30, 2027(forecast)
Also in Sorel-Tracy
- Replacement of the pile wall behind the water treatment plant$1.3M
- Renovation of the food service laundry at the hôpital de Sorel$1.2M
- Renewal of water pipes$806.2K
- Renovation and addition of two hemodialysis treatment stations at the Hôpital de Sorel$576.8K
- Ventilation Systems Repair in Components B and C$457.0K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58410 in the federal list. How to read these figures.