Replacement of the pile wall behind the water treatment plant

Sorel-Tracy, Quebec

completeDrinking WaterCWWF
Federal contribution
$1.3M
$1,344,267
Federal share50%

of $2.7M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 24, 2017
2017
Built

Approved 6 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
City of Sorel-Tracy
Construction start
Feb 6, 2017(actual)
Construction end
Nov 24, 2017(actual)

Against the original forecast

  • Construction start4 months lateforecast Oct 17, 2016
  • Construction end4 months earlyforecast Mar 31, 2018

Also in Sorel-Tracy

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48266 in the federal list. How to read these figures.