Ventilation Systems Repair in Components B and C

Sorel-Tracy, Quebec

completeVentilationCVRIS
Federal contribution
$457,000
Federal share52%

of $883.7K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 8, 2021
20222023
Built

Approved 4 months before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
Cégep Sorel-Tracy
Construction start
May 31, 2021(actual)
Construction end
Mar 23, 2023(actual)

Against the original forecast

  • Construction end3 months lateforecast Dec 31, 2022

Also in Sorel-Tracy

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59103 in the federal list. How to read these figures.