Ventilation Systems Repair in Components B and C
Federal contribution
$457,000
Federal share52%
of $883.7K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 8, 2021
20222023
Built
Approved 4 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Cégep Sorel-Tracy
- Construction start
- May 31, 2021(actual)
- Construction end
- Mar 23, 2023(actual)
Against the original forecast
- Construction end3 months lateforecast Dec 31, 2022
Also in Sorel-Tracy
- Construction of a New Sports Complex - Sorel-Tracy$10.4M
- Replacement of the pile wall behind the water treatment plant$1.3M
- Renovation of the food service laundry at the hôpital de Sorel$1.2M
- Renewal of water pipes$806.2K
- Renovation and addition of two hemodialysis treatment stations at the Hôpital de Sorel$576.8K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59103 in the federal list. How to read these figures.