Renovation of the food service laundry at the hôpital de Sorel

Sorel-Tracy, Quebec

completeVentilationCVRIS
Federal contribution
$1.2M
$1,205,600
Federal share80%

of $1.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 7, 2021
20222023
Built

Approved 4 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Jun 1, 2021(actual)
Construction end
Jun 23, 2023(actual)

Against the original forecast

  • Construction end21 months lateforecast Sep 30, 2021