Renovation and addition of two hemodialysis treatment stations at the Hôpital de Sorel
Federal contribution
$576,760
Federal share80%
of $721.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 7, 2021
20222023
Built
Approved 4 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Centre intégré de santé et de services sociaux de la Montérégie-Est
- Construction start
- Aug 2, 2021(actual)
- Construction end
- Dec 21, 2022(actual)
Against the original forecast
- Construction end11 months lateforecast Jan 19, 2022
Also in Sorel-Tracy