Medicine Hat Trail Rehabilitation and Pedestrian/Cycling Trail Development

Medicine Hat, Alberta

completeActive TransportationCVRIS
Federal contribution
$1.0M
$1,033,389
Federal share78%

of $1.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 16, 2021
2022
Built

Approved 4 weeks before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
City of Medicine Hat
Construction start
Jul 26, 2021(actual)
Construction end
Aug 2, 2022(actual)

Against the original forecast

  • Construction start3 months lateforecast Apr 30, 2021
  • Construction end8 weeks earlyforecast Sep 30, 2022