Medicine Hat Transit (MHT) Technology Upgrades
Federal contribution
$512,570
Federal share80%
of $640.7K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 16, 2021
20222023
Built
Approved 6 weeks before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- City of Medicine Hat
- Construction start
- Jul 6, 2022(actual)
- Construction end
- May 1, 2023(actual)
Against the original forecast
- Construction start5 weeks lateforecast Jun 1, 2022
- Construction end6 months lateforecast Nov 6, 2022
Also in Medicine Hat
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58498 in the federal list. How to read these figures.