Medicine Hat Echo Dale Reforestation

Medicine Hat, Alberta

completeDisaster MitigationCVRIS
Federal contribution
$318,773
Federal share73%

of $438.3K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 16, 2021
2022
Built

Approved 4 weeks before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
City of Medicine Hat
Construction start
Sep 13, 2021(actual)
Construction end
Sep 19, 2022(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Aug 16, 2021
  • Construction end4 months lateforecast May 31, 2022