Back to projects

Medicine Hat 533 - 1st Street SE, Municipal Office Addition

Medicine Hat, Alberta

completeAdministration, Emergency and Public WorksCVRIS
Federal contribution
$1.5M
$1,467,505
Federal share74%

of $2.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 16, 2021
2022
Built

Approved 4 weeks before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
City of Medicine Hat
Construction start
Jul 26, 2021(actual)
Construction end
Nov 22, 2022(actual)

Against the original forecast

  • Construction start4 months lateforecast Apr 1, 2021

Also in Medicine Hat