Rehabilitate Existing Sidewalks and Address Gaps for Sidewalk Development in Medicine Hat
Federal contribution
$783,090
Federal share80%
of $978.9K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 10, 2021
20222023
Built
Approved 4 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- City of Medicine Hat
- Construction start
- May 17, 2021(actual)
- Construction end
- Sep 30, 2023(actual)
Against the original forecast
- Construction start7 weeks lateforecast Apr 1, 2021
- Construction end2 months lateforecast Jul 30, 2023