Lethbridge Legacy Park Discovery Playground Construction
Federal contribution
$985,115
Federal share80%
of $1.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 16, 2021
20222023
Built
Approved 4 weeks before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- City of Lethbridge
- Construction start
- Jun 15, 2022(actual)
- Construction end
- May 24, 2023(actual)
Against the original forecast
- Construction start12 months lateforecast Jun 1, 2021
- Construction end19 months earlyforecast Dec 31, 2024