Lethbridge City Hall Cooling Tower Replacement

Lethbridge, Alberta

completeVentilationCVRIS
Federal contribution
$335,289
Federal share80%

of $419.1K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 16, 2021
20222023
Built

Approved 4 weeks before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
City of Lethbridge
Construction start
Oct 1, 2021(actual)
Construction end
Dec 31, 2022(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Sep 1, 2021

Also in Lethbridge

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58751 in the federal list. How to read these figures.