Lethbridge Fritz Sick Stream Boiler Replacement

Lethbridge, Alberta

completeRecreationCVRIS
Federal contribution
$432,000
Federal share80%

of $540.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 16, 2021
20222023
Built

Approved 4 weeks before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
City of Lethbridge
Construction start
Jul 5, 2021(actual)
Construction end
Jan 31, 2023(actual)

Against the original forecast

  • Construction start5 weeks lateforecast Jun 1, 2021
  • Construction end2 months lateforecast Nov 30, 2022