Lethbridge Lighting Retrofits at Multiple City Facilities

Lethbridge, Alberta

completeGreen EnergyCVRIS
Federal contribution
$1.5M
$1,480,000
Federal share80%

of $1.9M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 16, 2021
202220232024
Built

Approved 4 weeks before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
City of Lethbridge
Construction start
Dec 1, 2021(actual)
Construction end
Mar 31, 2024(actual)

Against the original forecast

  • Construction end9 months earlyforecast Dec 31, 2024