Yarmouth Regional Hospital (YRH) Energy Upgrades
Federal contribution
$432,791
Federal share80%
of $541.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 27, 2021
2022
Built
Approved 3 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Province of Nova Scotia
- Construction start
- Oct 4, 2021(actual)
- Construction end
- Oct 31, 2022(actual)
Against the original forecast
- Construction start2 months lateforecast Aug 3, 2021
- Construction end4 months lateforecast Jun 30, 2022
Also in Yarmouth
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59301 in the federal list. How to read these figures.