Municipal Administration Office Upgrade
Federal contribution
$128,099
Federal share80%
of $160.1K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 29, 2021
2022
Built
Approved 3 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Municipality of West Perth
- Construction start
- Jun 1, 2022(actual)
- Construction end
- Jul 26, 2022(actual)