Back to projects

Colonization Road West Sidewalk Linking

Fort Frances, Ontario

completeActive TransportationCVRIS
Federal contribution
$147,789
Federal share80%

of $184.7K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 7, 2021
Built

Approved 2 months before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
Town of Fort Frances
Construction start
Jun 14, 2021(actual)
Construction end
Oct 13, 2021(actual)

Against the original forecast

  • Construction start6 weeks lateforecast May 3, 2021
  • Construction end2 weeks earlyforecast Oct 29, 2021

Also in Fort Frances