North Okanagan - Shuswap North Okanagan Rail Trail: Enderby-Splatsin Section
Federal contribution
$367,249
Federal share80%
of $459.1K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 15, 2021
202220232024
Built
Approved 7 weeks before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Regional District of North Okanagan
- Construction start
- Jun 27, 2023(actual)
- Construction end
- Dec 8, 2023(actual)
Against the original forecast
- Construction start3 months lateforecast Mar 15, 2023
Also in Enderby