Retrofits/Repairs/Upgrade Municipal Infrastructure
Federal contribution
$5.3M
$5,254,361
Federal share80%
of $6.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 13, 2021
2022202320242025
Built
Approved 3 weeks before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- York Region
- Construction start
- Aug 20, 2021(actual)
- Construction end
- Dec 31, 2024(actual)
Also in York
- Regional Municipality of York - Transit Fleet Electrification$76.0M
- York Durham Sewage System Forcemain Twinning$43.3M
- Yonge North Subway Extension - Planning and Preliminary Engineering$36.3M
- Groundwater Supply System Improvements to Mitigate Impacts of Extreme Weather Events on Lake Based Supplies$18.1M
- Rehabilitation of the York-Durham Sewer on 16th Avenue the City of Markham$12.1M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60962 in the federal list. How to read these figures.