Main Street Road Upgrade
Bishop's Falls, Newfoundland and Labrador
Federal contribution
$95,282
Federal share33%
of $285.8K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 13, 2021
2022
Built
Approved 5 weeks before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Town of Bishops Falls
- Construction start
- Sep 17, 2022(actual)
- Construction end
- Oct 27, 2022(actual)
Against the original forecast
- Construction start6 months lateforecast Apr 1, 2022
- Construction end8 weeks lateforecast Aug 31, 2022
Also in Bishop's Falls
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 61048 in the federal list. How to read these figures.