Whistler - Sea to Sky Electric Vehicle Network Expansion
Federal contribution
$1.2M
$1,190,296
Federal share40%
of $3.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 27, 2022
2023202420252026
BuiltForecast
Approved 2 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Resort Municipality of Whistler
- Construction start
- Aug 4, 2023(actual)
- Construction end
- Mar 31, 2026(forecast)
Against the original forecast
- Construction start7 weeks lateforecast Jun 19, 2023
Also in Whistler
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 62090 in the federal list. How to read these figures.