Public transit expansion system for rural areas surrounding Cranbrook, BC

Cranbrook, British Columbia

completeCapacity BuildingRTSF
Federal contribution
$40,000
Federal share100%

of $40.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 10, 2024
20232024
Built

Approved 2.2 years before the announcement.

Program
Permanent Public Transit Program
Ultimate recipient
City of Cranbrook
Construction start
Feb 1, 2023(actual)
Construction end
May 24, 2024(actual)

Against the original forecast

  • Construction start10 months lateforecast Apr 1, 2022
  • Construction end15 months lateforecast Mar 1, 2023