La Verendrye Parkway Expansion - Feasibility Study and Conceptual Design

Fort Frances, Ontario

completeCapacity BuildingATF
Federal contribution
$50,000
Federal share100%

of $50.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 19, 2024
20232024
Built

Approved 21 months before the announcement.

Program
Active Transportation Fund
Construction start
Feb 13, 2023(actual)
Construction end
Feb 5, 2024(actual)

Against the original forecast

  • Construction start9 months lateforecast May 2, 2022
  • Construction end15 months lateforecast Nov 2, 2022