Active Transportation Masterplan
Federal contribution
$49,912
Federal share100%
of $49.9K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedDec 19, 2022
2023202420252026
Built
Approved 6 months before the announcement.
- Program
- Active Transportation Fund
- Ultimate recipient
- City of Cranbrook
- Construction start
- Nov 29, 2022(actual)
- Construction end
- Mar 30, 2026(actual)
Against the original forecast
- Construction start4 months lateforecast Aug 12, 2022
- Construction end2.7 years lateforecast Jun 30, 2023
Also in Cranbrook
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 63798 in the federal list. How to read these figures.