Purchase of vehicles to expand on-demand services in the St. Margaret's Bay area, Nova Scotia
Federal contribution
$144,526
Federal share77%
of $188.4K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedDec 12, 2024
202320242025
Built
Approved 2 years before the announcement.
- Program
- Permanent Public Transit Program
- Ultimate recipient
- BayRides
- Construction start
- Apr 20, 2023(actual)
- Construction end
- Dec 12, 2024(actual)
Against the original forecast
- Construction start8 months lateforecast Sep 1, 2022
- Construction end3 months lateforecast Sep 1, 2024
Also in Chester
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 63908 in the federal list. How to read these figures.