Purchase an accessible vehicle for members of the Xatsull First Nation to access health and medical appointments in British Columbia

Williams Lake, British Columbia

completePublic TransitRTSF
Federal contribution
$107,669
Federal share100%

of $107.7K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 10, 2024
20232024
Built

Approved 17 months before the announcement.

Program
Permanent Public Transit Program
Construction start
Mar 1, 2023(actual)
Construction end
Nov 1, 2023(actual)

Against the original forecast

  • Construction start7 months lateforecast Aug 1, 2022
  • Construction end5 months earlyforecast Mar 31, 2024

Also in Williams Lake

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 64003 in the federal list. How to read these figures.