Melrose Culvert Replacement
Trinity Bay North, Newfoundland and Labrador
Federal contribution
$24,688
Federal share22%
of $113.4K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 7, 2024
20232024
Built
Approved 19 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of Trinity Bay North
- Construction start
- Jun 26, 2023(actual)
- Construction end
- Sep 15, 2023(actual)
Against the original forecast
- Construction start3 weeks lateforecast Jun 6, 2023
- Construction end3 months lateforecast Jun 30, 2023