Embracing the Future while Remembering our Past: Stirling-Rawdon Theatre and Library Retrofit
Federal contribution
$240,311
Federal share80%
of $300.4K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 3, 2025
202320242025
Built
Approved 2.1 years before the announcement.
- Program
- Green and Inclusive Community Buildings Program
- Ultimate recipient
- Township of Stirling-Rawdon
- Construction start
- May 1, 2024(actual)
- Construction end
- May 1, 2025(actual)
Against the original forecast
- Construction start2 years lateforecast May 2, 2022
- Construction end2.3 years lateforecast Dec 30, 2022
Also in Stirling-Rawdon
- Ridge Road Rehabilitation$1.2M
- Replacement of the Watermain along North, Mill, Front and Henry Street$528.0K
- Rehabilitation of Outdoor space$80.0K
- Drinking Water Feasibility Study to access the options of providing an alternate source of drinking water at our present facility at 93 Elizabeth Street.$37.5K
- Preliminary Design for Upgrade the Stormwater, Water and Wastewater Infrastructure on Baker Street$12.5K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 65526 in the federal list. How to read these figures.