Wetland Restoration on AQAM Lands
Federal contribution
$1.0M
$1,000,000
Federal share73%
of $1.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedDec 6, 2024
202420252026
Built
Approved 18 months before the announcement.
- Program
- Natural Infrastructure Fund
- Ultimate recipient
- ¿aq¿am Community I.R.1
- Construction start
- Oct 16, 2024(actual)
- Construction end
- Dec 31, 2025(actual)
Also in Cranbrook