City of Powell River - Mid-Level Connector Multi-Use Pathway
Powell River, British Columbia
Federal contribution
$150,000
Federal share10%
of $1.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 6, 2024
today
20242025202620272028
BuiltForecast
Approved 12 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- City of Powell River
- Construction start
- Feb 18, 2025(actual)
- Construction end
- Nov 30, 2027(forecast)
Against the original forecast
- Construction start3 months lateforecast Dec 1, 2024
Also in Powell River
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 66991 in the federal list. How to read these figures.