Town of Yarmouth Transit Service Upgrade
Federal contribution
$168,000
Federal share40%
of $420.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 29, 2024
2024
Built
Approved 16 months before the announcement.
- Program
- Public Transit Infrastructure Stream
- Ultimate recipient
- Town of Yarmouth
- Construction start
- Jul 14, 2023(actual)
- Construction end
- Aug 30, 2024(actual)
Against the original forecast
- Construction start3 months lateforecast Apr 1, 2023
- Construction end4 months earlyforecast Dec 31, 2024
Also in Yarmouth
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 67680 in the federal list. How to read these figures.