Back to projects

Transit Scheduling System

Medicine Hat, Alberta

underwayPublic TransitPTIS
Federal contribution
$38,400
Federal share40%

of $96.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 26, 2024
today
20242025202620272028
BuiltForecast

Approved 11 months before the announcement.

Program
Public Transit Infrastructure Stream
Ultimate recipient
City of Medicine Hat
Construction start
Apr 16, 2024(actual)
Construction end
Apr 16, 2028(forecast)

Against the original forecast

  • Construction start7 months lateforecast Oct 1, 2023