Windmill Road Water and Sewer
Paradise, Newfoundland and Labrador
Federal contribution
$317,392
Federal share40%
of $793.5K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedDec 5, 2024
202420252026
BuiltForecast
Approved 16 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of Paradise
- Construction start
- Apr 26, 2026(actual)
- Construction end
- Jun 29, 2026(forecast)
Against the original forecast
- Construction start3 weeks earlyforecast May 18, 2026