Bayview Heights Water and Sewer

Paradise, Newfoundland and Labrador

completeWastewaterGIS
Federal contribution
$220,905
Federal share40%

of $552.3K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedDec 5, 2024
20242025
Built

Approved 16 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of Paradise
Construction start
Apr 23, 2025(actual)
Construction end
Aug 15, 2025(actual)

Against the original forecast

  • Construction start8 weeks lateforecast Mar 1, 2025
  • Construction end2 months lateforecast Jun 6, 2025

Also in Paradise

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 67954 in the federal list. How to read these figures.