Bayview Heights Water and Sewer
Paradise, Newfoundland and Labrador
Federal contribution
$220,905
Federal share40%
of $552.3K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedDec 5, 2024
20242025
Built
Approved 16 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of Paradise
- Construction start
- Apr 23, 2025(actual)
- Construction end
- Aug 15, 2025(actual)
Against the original forecast
- Construction start8 weeks lateforecast Mar 1, 2025
- Construction end2 months lateforecast Jun 6, 2025
Also in Paradise
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 67954 in the federal list. How to read these figures.