11projects·$5.4Mfederal of $10.8M eligible
2017 Sanitary Sewer Study
$51.5KBotwood · Wastewater
complete·approved 2017
Septic Tank - Circular Rd Outflow
$52.9KBotwood · Wastewater
complete·approved 2018
Fernwood Drive Sanitary Sewer
$143.6KBotwood · Wastewater
complete·approved 2018
Confederation Place - Water, Sewer, and Road
$196.5KBotwood · Wastewater
complete·approved 2018
Watermain Replacement Water Street Valley Road Intersection (2022)
$230.7KBotwood · Drinking Water
complete·approved 2022
2017 Sanitary Sewer Outfall - Phase 1 Circular Road
$249.8KBotwood · Wastewater
complete·approved 2017
Water Main Replacement & Associated Upgrades - Sacrey's Road
$358.7KBotwood · Drinking Water
complete·approved 2020
Water Main Replacement & Associated Upgrades - Church Road
$642.2KBotwood · Drinking Water
complete·approved 2021
Ventilation Upgrades at Various Health Centres
$800.0KBotwood +3 · Ventilation
complete·approved 2021
Commonwealth Drive Watermain Replacement
$809.7KBotwood · Drinking Water
complete·approved 2023
Various School Ventilation Upgrades
$1.9MBishop's Falls +9 · Ventilation
complete·approved 2022
| Project | Location | Category | Status | Federal | Total | Approved |
|---|---|---|---|---|---|---|
| 2017 Sanitary Sewer Study Town of Botwood | Botwood | Wastewater | complete | $51.5K | $102.9K | 2017 |
| Septic Tank - Circular Rd Outflow Town of Botwood | Botwood | Wastewater | complete | $52.9K | $158.7K | 2018 |
| Fernwood Drive Sanitary Sewer Town of Botwood | Botwood | Wastewater | complete | $143.6K | $435.3K | 2018 |
| Confederation Place - Water, Sewer, and Road Town of Botwood | Botwood | Wastewater | complete | $196.5K | $589.4K | 2018 |
| Watermain Replacement Water Street Valley Road Intersection (2022) Town of Botwood | Botwood | Drinking Water | complete | $230.7K | $576.6K | 2022 |
| 2017 Sanitary Sewer Outfall - Phase 1 Circular Road Town of Botwood | Botwood | Wastewater | complete | $249.8K | $798.0K | 2017 |
| Water Main Replacement & Associated Upgrades - Sacrey's Road Town of Botwood | Botwood | Drinking Water | complete | $358.7K | $1.1M | 2020 |
| Water Main Replacement & Associated Upgrades - Church Road Town of Botwood | Botwood | Drinking Water | complete | $642.2K | $1.6M | 2021 |
| Ventilation Upgrades at Various Health Centres Government of Newfoundland and Labrador | Botwood +3 more | Ventilation | complete | $800.0K | $1.0M | 2021 |
| Commonwealth Drive Watermain Replacement Town of Botwood | Botwood | Drinking Water | complete | $809.7K | $2.0M | 2023 |
| Various School Ventilation Upgrades Newfoundland and Labrador English School District | Bishop's Falls +9 more | Ventilation | complete | $1.9M | $2.4M | 2022 |