14projects·$6.3Mfederal of $13.2M eligible
Mattawan Asset Management
$3.4KMattawan · Capacity Building
complete·approved 2007
Calvin Asset Management
$3.5KMattawa · Capacity Building
complete·approved 2007
Township of Papineau-Cameron Asset Management
$3.7KMattawa · Capacity Building
complete·approved 2007
Improvements to Moosehead Road
$14.9KMattawa · Highways and Roads
complete·approved 2006
Water Treatment Plant Chlorination Analysis Improvements
$40.7KMattawa · Drinking Water
complete·approved 2018
Water Storage Reservoir Upgrades including provision for Emergency Backup Power, SCADA Improvements, Replacement of Corroded Piping, Valves, and Access Hatches, and Construction of Access Road
$44.1KMattawa · Drinking Water
complete·approved 2018
Rehabilitation of the Municipal Hall
$80.0KMattawan · Administration, Emergency and Public Works
complete·approved 2021
Construction of Turcotte Park Road Sidewalk
$80.0KMattawa · Active Transportation
complete·approved 2021
Construction of Sand Dome
$89.2KMattawa · Highways and Roads
complete·approved 2009
Samuel de Champlain Museum and Information Centre
$150.0KMattawa · Culture
complete·approved 2010
Replacement of Pautois Bridge #5
$297.6KMattawa · Highways and Roads
complete·approved 2009
Replacement of Murphy Road Bridge
$1.1MMattawan · Highways and Roads
complete·approved 2020
Replacement of Highway 17 Sewer and Waterlines
$1.5MMattawa · Drinking Water
complete·approved 2009
Reconstruction of Dorion Road Hill
$2.9MMattawa · Highways and Roads
underway·approved 2020
| Project | Location | Category | Status | Federal | Total | Approved |
|---|---|---|---|---|---|---|
| Mattawan Asset Management Township of Mattawan | Mattawan | Capacity Building | complete | $3.4K | $10.3K | 2007 |
| Calvin Asset Management Municipality of Calvin | Mattawa | Capacity Building | complete | $3.5K | $10.4K | 2007 |
| Township of Papineau-Cameron Asset Management Township of Papineau-Cameron | Mattawa | Capacity Building | complete | $3.7K | $11.0K | 2007 |
| Improvements to Moosehead Road Township of Mattawan | Mattawa | Highways and Roads | complete | $14.9K | $44.8K | 2006 |
| Water Treatment Plant Chlorination Analysis Improvements Town of Mattawa | Mattawa | Drinking Water | complete | $40.7K | $87.5K | 2018 |
| Water Storage Reservoir Upgrades including provision for Emergency Backup Power, SCADA Improvements, Replacement of Corroded Piping, Valves, and Access Hatches, and Construction of Access Road Town of Mattawa | Mattawa | Drinking Water | complete | $44.1K | $126.5K | 2018 |
| Rehabilitation of the Municipal Hall The Corporation of the Municipality of Mattawan | Mattawan | Administration, Emergency and Public Works | complete | $80.0K | $100.0K | 2021 |
| Construction of Turcotte Park Road Sidewalk Town of Mattawa | Mattawa | Active Transportation | complete | $80.0K | $100.0K | 2021 |
| Construction of Sand Dome Township of Papineau-Cameron | Mattawa | Highways and Roads | complete | $89.2K | $267.5K | 2009 |
| Samuel de Champlain Museum and Information Centre Government of Ontario | Mattawa | Culture | complete | $150.0K | $300.0K | 2010 |
| Replacement of Pautois Bridge #5 Township of Calvin | Mattawa | Highways and Roads | complete | $297.6K | $892.9K | 2009 |
| Replacement of Murphy Road Bridge The Corporation of the Municipality of Mattawan | Mattawan | Highways and Roads | complete | $1.1M | $1.9M | 2020 |
| Replacement of Highway 17 Sewer and Waterlines Town of Mattawa | Mattawa | Drinking Water | complete | $1.5M | $4.6M | 2009 |
| Reconstruction of Dorion Road Hill Town of Mattawa | Mattawa | Highways and Roads | underway | $2.9M | $4.8M | 2020 |