Rehabilitation/replacement of three culverts in Oakville
Federal contribution
$331,667
Federal share33%
of $995.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 25, 2005
2006200820102012
Built
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Town of Oakville
- Construction start
- Jan 1, 2006(actual)
- Construction end
- Dec 31, 2011(actual)
Against the original forecast
- Construction end15 months earlyforecast Mar 31, 2013
Also in Oakville
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 11976 in the federal list. How to read these figures.