Back to projects

Water and Sewer – Riverhead and Harvey Street Area

Harbour Grace, Newfoundland and Labrador

completeDrinking WaterMRIF
Federal contribution
$344,724
Federal share33%

of $1.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 29, 2008
Built

Approved 6 weeks before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Town of Harbour Grace
Construction start
Feb 1, 2008(actual)
Construction end
Nov 30, 2008(actual)

Against the original forecast

  • Construction end4 weeks lateforecast Nov 1, 2008