Water and Sewer Upgrading – Harvey Street

Harbour Grace, Newfoundland and Labrador

completeWastewaterGIS
Federal contribution
$324,702
Federal share32%

of $1.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 26, 2019
20202021
Built

Approved 4 weeks before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of Harbour Grace
Construction start
Jul 22, 2020(actual)
Construction end
Aug 25, 2021(actual)

Against the original forecast

  • Construction start7 weeks lateforecast Jun 1, 2020
  • Construction end8 weeks lateforecast Jun 30, 2021

Also in Harbour Grace

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 53888 in the federal list. How to read these figures.