Water and Sewer Upgrading Harvey Street
Harbour Grace, Newfoundland and Labrador
Federal contribution
$324,702
Federal share32%
of $1.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 26, 2019
20202021
Built
Approved 4 weeks before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of Harbour Grace
- Construction start
- Jul 22, 2020(actual)
- Construction end
- Aug 25, 2021(actual)
Against the original forecast
- Construction start7 weeks lateforecast Jun 1, 2020
- Construction end8 weeks lateforecast Jun 30, 2021
Also in Harbour Grace
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 53888 in the federal list. How to read these figures.