Kitchen's Hill - Water & Sewer System Upgrade
Harbour Grace, Newfoundland and Labrador
Federal contribution
$426,400
Federal share31%
of $1.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 6, 2018
201920202021
Built
Approved 3 months before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Town of Harbour Grace
- Construction start
- Nov 19, 2018(actual)
- Construction end
- May 1, 2021(actual)
Against the original forecast
- Construction start6 months earlyforecast May 30, 2019
- Construction end8 months earlyforecast Dec 31, 2021