Kitchen's Hill - Water & Sewer System Upgrade

Harbour Grace, Newfoundland and Labrador

completeDrinking WaterSCF
Federal contribution
$426,400
Federal share31%

of $1.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 6, 2018
201920202021
Built

Approved 3 months before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Town of Harbour Grace
Construction start
Nov 19, 2018(actual)
Construction end
May 1, 2021(actual)

Against the original forecast

  • Construction start6 months earlyforecast May 30, 2019
  • Construction end8 months earlyforecast Dec 31, 2021

Also in Harbour Grace

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 52217 in the federal list. How to read these figures.