Sanitary and Storm Sewer Outfall Relocation

Harbour Grace, Newfoundland and Labrador

completeWastewaterGIS
Federal contribution
$349,947
Federal share31%

of $1.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 28, 2022
20222023
Built

Approved 7 weeks before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of Harbour Grace
Construction start
Apr 24, 2023(actual)
Construction end
Jul 27, 2023(actual)

Against the original forecast

  • Construction end5 months earlyforecast Dec 31, 2023