LeMarchant Street Water & Sewer Upgrading
Harbour Grace, Newfoundland and Labrador
Federal contribution
$398,938
Federal share40%
of $997.3K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedDec 5, 2024
20242025
Built
Approved 16 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of Harbour Grace
- Construction start
- Sep 16, 2024(actual)
- Construction end
- Jun 1, 2025(actual)
Against the original forecast
- Construction start5 months lateforecast May 1, 2024
Also in Harbour Grace
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 67622 in the federal list. How to read these figures.