Back to projects

Harvey Street Phase V - Sewer, Water & Street Upgrading

Harbour Grace, Newfoundland and Labrador

completeDrinking WaterGIS
Federal contribution
$692,018
Federal share33%

of $2.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 18, 2020
202120222023
Built

Approved 3 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of Harbour Grace
Construction start
Jun 13, 2022(actual)
Construction end
Dec 9, 2022(actual)

Against the original forecast

  • Construction start4 weeks lateforecast May 15, 2022
  • Construction end10 months earlyforecast Sep 30, 2023

Also in Harbour Grace

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56797 in the federal list. How to read these figures.