Harvey Street Phase V - Sewer, Water & Street Upgrading
Harbour Grace, Newfoundland and Labrador
Federal contribution
$692,018
Federal share33%
of $2.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 18, 2020
202120222023
Built
Approved 3 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of Harbour Grace
- Construction start
- Jun 13, 2022(actual)
- Construction end
- Dec 9, 2022(actual)
Against the original forecast
- Construction start4 weeks lateforecast May 15, 2022
- Construction end10 months earlyforecast Sep 30, 2023