Back to projects

New Watermain to Connect to Fortune’s Water Supply

Grand Bank, Newfoundland and Labrador

completeDrinking WaterMRIF
Federal contribution
$571,959
Federal share25%

of $2.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 15, 2007
2007200820092010
Built

Approved 8 weeks before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Town of Grand Bank
Construction start
Dec 19, 2006(actual)
Construction end
Jun 7, 2010(actual)

Against the original forecast

  • Construction start4 months earlyforecast May 1, 2007
  • Construction end2.6 years lateforecast Nov 1, 2007