Riverside Drive East Phase ll - Fish Plant Water Main Replacement

Grand Bank, Newfoundland and Labrador

completeWastewaterGIS
Federal contribution
$580,594
Federal share40%

of $1.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 4, 2025
20242025
Built

Approved 24 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of Grand Bank
Construction start
Jun 10, 2024(actual)
Construction end
Jul 31, 2024(actual)

Against the original forecast

  • Construction start6 months lateforecast Dec 7, 2023
  • Construction end5 months lateforecast Feb 15, 2024

Also in Grand Bank

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 66517 in the federal list. How to read these figures.